Cedar Park, TX Stonehaven at Cedar Park
At every stage of the process, we strive to deliver unsurpassed customer service that exceeds the expectations of our customers. Check out our example below of one project we are proud to share with you. For more information on our products & services, you can read about them here or contact us.
Project Goals
Stonehaven at Cedar Park, TX use one main utility water meter to supply the utilities to the building. The customer wanted to bill back the water utility costs to each tenant based on how much they individually consume. The request was for a remotely accessible, wireless sub-metering system to meter the water usage for each apartment unit.
Scope of Project
- 121 Next Century Cold Water Meters
- Tehama Wireless Reading System
- Onsite Consultation, Installation, Commissioning Services, and Meter Installation Training
Schedule
- Equipment Supplied February 2020
- Installation and Commissioning Completed April 2020
Result
New construction apartment with metering system supplied in time for project plumbing contractors to install meters during plumbing installation. Next Century water meters and a Tehama wireless metering reading system combines superior quality with the best value within the industry. System read on line each month to bill residents for their actual water usage.